The project is an entire community with 1,728 hotel rooms, services and amenities to host guests, consultants, engineers and senior managers working in the remote city of Al Ruwais for ADNOC.
The entire project was designed and delivered by DuBox and the Amana Group, beginning in Oct 2014 with an 80-week programme. Occupancies of the first three buildings were taking place only 14 months from project start.
85% of the entire built area was completed offsite in our factory in Dubai (360 KM away from site), utilising 32% less labour on and off site.
To find out more, visit https://www.dubox.me/projects/
89,750
Total Area (m²)
80
Weeks Duration
2015
Completion Year